Prince George’s County Public Schools is replacing the 344,875-square-foot Suitland High School campus with a new 389,108-square-foot facility that will house both the Comprehensive High School (CHS) and the Center for Visual and Performing Arts (CVPA), serving 1,500 CHS students and 500 CVPA students. Career and Technical Education (CTE) programs were relocated to Crossland High School in 2022, establishing it as the county’s southern CTE hub. The new Suitland High School will feature modern learning environments and amenities to support academic and arts-focused instruction.

school building construction rendition

Where We Are Now

project status indicator illustration showing in Construction phase

Construction teams move forward with implementing the school’s design.

Estimated Completion: 2027

Last Updated: June 25, 2026

Project At-A-Glance

ADDRESS
5200 Silver Hill Road, Suitland, MD 20747

PROJECT TYPE
Replacement

PROJECT BUDGET
$335,000,000

ARCHITECT
Cox Graae + Spack Architects

GENERAL CONTRACTOR
Turner Corenic Joint Venture

PROJECT MANAGER
Anoop Gupta

PRINCIPAL
Maurice Wright

NEIGHBORHOOD
Suitland, Arnold Heights

SCHOOL BOARD DISTRICT
District 7

COUNTY COUNCIL DISTRICT
District 7

STATE LEGISLATIVE DISTRICT
District 24

Documents & Presentations

Live Construction Camera 1  Live Construction Camera 2

Project Update Meeting - 09/29/2025 | Recording; Presentation (English, Spanish, French); Q&A (English, Spanish, French)

Swing Information Session - 03/25/2025 | Recording (English, Spanish); Presentation (English, Spanish, French); Q&A (English, Spanish, French)

Project Update Meeting - 03/11/2025 | Recording; Presentation (English, Spanish, French); Q&A (English, Spanish, French)

Project Update Meeting - 09/24/2024 | Recording; Presentation (English, Spanish, French); Q&A (English, Spanish, French)

Project Update Meeting - 04/02/2024 | Recording; Presentation (English, Spanish, French); Q&A (English, Spanish, French)

Project Update Meeting - 10/25/2023 | Recording; Presentation (English, Spanish, French); Q&A (English, Spanish, French)

Project Update Meeting - 06/05/2023 | Recording; Presentation (English, Spanish, French); Q&A (English, Spanish, French)

Construction Update Meeting - 12/07/2022 | Recording; Presentation (English, Spanish, French); Q&A (English, Spanish, French)

Design and Construction Town Hall - 04/05/2022 | Recording; Presentation (English, Spanish, French); Q&A (English, Spanish, French)

Schematic Design Summary - 10/28/2020 | Summary

Feasibility Study - 03/07/2019 | Feasibility Study

Suitland CVPA Options Analysis - 04/05/2017 | BrochureFinal Report